Conventional Process
![]() |
1.Product design 1day |
![]() |
2.Die design 5days |
![]() |
3.Die material purchase 7days |
![]() |
4.Machining 10days |
![]() |
5.Quenching 12days |
![]() |
6.Wire-EDM 15days |
![]() |
7.Grind 17days |
![]() |
8.Assemble 19days |
![]() |
9.Punch trial 21days |
![]() |
10.Production 26days |
![]() |
11.Transport 29days |
![]() |
12.Delivery total: 29days |
Dieless Forming(forming without die)
![]() |
1.Product design 1day |
![]() |
2.Dieless Forming 6days |
![]() |
3.Transport 9days |
![]() |
4.Delivery total: 9days |
Products manufactured with Dieless Forming method can be delivered
18 days earlier.
We do machine processing and assembly of precision sheet metal parts primarily and its associated parts.
We deliver high quality products to you in two days at an average.